Project comprises the design, construction and 1 year maintenance of Ceremonial National Day Road (Link Road between Dukhan Road and North Road).
Scope:
- Design of 1,6 km Connection Road between Dukhan Road and Ceremonial National Day Road,
- Design, construction and 1 year maintenance of ;
- 10,1 km Dual 3 lanes Highway,
- 10,5 km two lane Frontage Roads,
- 15,5 km two lane Service Roads with 6 ea. Roundabouts,
- 2,8 km Dual 2 lanes Underpass Roads
- 18 km Camel Road,
- 18 km Walkway and Jogging Track,
- 21,2 km Bicycle Path,
- 2 ea. Vehicle Underpass,
- 4 ea. Pedestrian Underpass,
- Road Lighting works,
- Grading of the Ceremony Areas,
- Drainage Works,
- Concrete Barriers and Curbs,
- 18 km Potable Water Line,
- 21 ea. Tiolet Units each having 6 ea. Toilets and 10 ea. Wash Basin
|