TURKEY - ÇİFTEHAN - POZANTI MOTORWAY
 
Tekfen Job No   230
 
Location   Niğde, Turkey
 
Client   General Directorate of Highways
 
Contractor   Tekfen Construction and Installation Co., Inc. - Tübin-Özdemir J.V.
 
Final Project Value   US$ 310.935.120
 
Tekfen Portion   70,65%
 
Commencement   14/10/1998
 
Completion   31/12/2013
 
Having successfully completed the US$ 2 Billion worth, 258 km long Tarsus-Adana-Gaziantep, TAG Motorway scheme as of September 2002, Tekfen Construction and Installation Co., Inc. sails to new challenging horizons. TAG Motorway was the largest project implemented by Tekfen within the scope of a single contract.

Presently, as a member of two separate J.V. groups, Tekfen has undertaken major responsibilities at three new motorway projects, all being located along the rough and mountainous regions of Turkey.

HIGHLIGHTS

18,5 km 2 x 3 lane motorway,
2,5 km 1 x 2 lane connection road,
14 viaducts with total length of 4.430 m,
4 overpasses,
3 underpasses,
7.550 m2 reinforced earth retaining wall,
2 double tube tunnels with total length of 842 m.